Fall Semester Update

Throughout the fall semester, significant progress was made in data collection, site analysis, and the development of design solutions to improve hydrological and transportation conditions to 2nd and 3rd Ave. In both areas, three alternative designs were proposed to advance public safety. The existing Site layout is shown in the image below.

An image of the existing site layout is displayed. The image contains two boxes, one with Google map arrows coming out pointing to the intersection of 2nd and 3rd Avenue. In the second image, the Gowanus Canal is visible in the left portion of the image, with a red arrow pointing to it. Two major intersections are highlighted with red circles: one at 2nd Avenue and 9th Street, and another at 3rd Avenue and 9th Street.
Existing Site Layout

The intersections at 9th Street and 2nd and 3rd Avenue experience heavy congestion with traffic volumes at 10889 AADT, limited pedestrian safety infrastructure, and insufficient accessibility for Americans with Disabilities (ADA). The objective of this project is to develop an integrated hydrologic and transportation design that improves drainage efficiency and enhances multimodal traffic flow.

The first alternative adds a continuous roundabout with a center median along Ninth Street. Roundabouts at Second and Third Avenue would reduce stop-and-go traffic and improve flow. The median would limit left turns, improve safety, and give pedestrians a protected waiting area.

The image portrays the first alternative design. The design proposes turning the 2 proposed intersections, 2nd avenue on the left and 3rd avenue on the right, into an extended roundabout to optimize traffic flow in this area. The image shows both of the intersections redesigned into unsignalized roundabouts that are connected with a green median throughout 9th street.
Alternative Design 1

The second alternative uses a one-way roundabout at the 2nd Avenue intersection, with Ninth Street also operating one-way. This design improves traffic flow and reduces congestion by replacing a standard intersection with a smoother, curved layout. The roundabout reduces conflict points and makes merging easier. Slower speeds and clear crosswalks also improve safety for pedestrians, cyclists, and drivers.

The image portrays the second alternative design. This design proposes turning the 2nd avenue intersection on the left into a roundabout, while turning 9th street into a oneway, and keeping the 3rd avenue intersection on the right unchanged. The image shows how a one way street going into a roundabout would mean cars would be able to continue going straight, turn left, or turn right. They would not be able to go all the way around which would minimize the traffic volume in this area.
Alternative Design 2

The third alternative makes Ninth Street a Complete Street and converts it to a one-way road. The intersection would be upgraded to ADA standards, and new features like a median, bike lanes, and bollards would improve safety for cyclists and pedestrians. A dedicated bus-only lane would support frequent transit use, and a new parking lot would help reduce illegal or unsafe street parking. Added trees and green space would improve sustainability and create a more pedestrian-friendly environment. Vehicle movement would be limited so it doesn’t overpower pedestrian and cyclist activity.

This image portrays the third alternative design. The design proposes turning 9th street into a complete street which would turn it into a one way with traffic only being able to go right to left. This option would also take away parking spaces due to added bike and bus lanes; therefore, on the image ,to the right of 9th street, a parking lot is proposed to not inconvenience those who commonly use those parking spots. Further up on the image, next to the parking lot, a park is also proposed to add greenspace and sustainability to the community.
Alternative Design 3

Traffic counts along 9th Street showed high pedestrian and bicycle use along with moderate traffic volumes. For these reasons, Alternative Design 3: Complete Street was chosen because it focused on the safety of pedestrians and cyclists, calming traffic, and sustainability for the future with good vehicle throughput.

To evaluate the most optimal stormwater mitigation design alternative, a watershed analysis was conducted at the Gowanus canal site. The hydrological modeling programs HEC-HMS and HEC-RAS, both widely used in industry, were utilized to simulate conditions of a 24‑hour, 100‑year storm event. Based on this storm event HEC-HMS estimated a peak discharge of 2875.4 cubic feet per second and direct run-off volume of 1001.6 acre-feet. HEC-RAS was able to determine that during the 24-hour 100 year storm event the peak discharge would be about 1403.76 cubic feet per second. These results influenced the decision to redesign the existing piping network to more effectively accommodate increased stormwater capacity, especially during extreme weather events. 

The selected design alternative for the selected transportation improvements as well as the hydrological alternative is depicted in the provided image. The potential piping redesign geometry is included within the image in the form of red dotted lines. Additionally, the placement of the proposed park shaded in green and proposed parking lot shaded in blue are also indicated.

This image portrays the final design that was chosen which was the third alternative. The design proposes turning 9th street into a complete street which would turn it into a one way with traffic only being able to go right to left. This option would also take away parking spaces due to added bike and bus lanes; therefore, on the image ,to the right of 9th street, a parking lot is proposed to not inconvenience those who commonly use those parking spots. Further up on the image, next to the parking lot, a park is also proposed to add greenspace and sustainability to the community. There are also red lines going through all streets present on the image that represent the piping network, with red circles on the intersections that represent the manholes where the piping systems connect.
Final Design Selection

The team concluded the semester with a final fall presentation of engineering services, which can be accessed through the link below.

Improvements to Hydrological and Transportation Improvements to 3rd and 2nd Ave in Brooklyn, NY Final Fall Presentation