Project Timeline


September

  • Created Requirements and Justifications with sources
  • Created Slide deck with Requirements and Justifications for presentation 1
  • Revised Requirements and Justifications and added constraints

October

  • Created Gantt chart based off initial
  • Completed safety survey
  • Took initial measurements of hospital beds
  • Created Initial lifting devices based off lifting concept
  • Added verifications and Validations based off of initial design ideas of Lifting machine
  • Updated Budget chart for initial project of lifting device
  • Generation of new winch Design based off of initial design concepts
  • Generation of Device B and Requirements
  • Generation of New Solidworks drawings for Device B, Device A, and Hospital table
  • Creation of Decision Matrix of off Designs
  • Presented initial design proposal

November

  • Development of finalized design
  • Created new idea to base budget off new device
  • Development initial Anysis testing for table
  • Creation of finalized budget based off of initial simulations
  • Development of Abstract for device

December

  • Initial final design completed
  • Hazard Analysis completed
  • Team presented final design to peers and faculty
  • Completion of initial device design report

January

  • Parts and budget finalized
  • Parts ordered for device design

February

  • NEBEC Abstract created
  • Alterations made to Device A and setup
  • Development of Testing protocol

March

  • Final designs made for device A & B
  • Verifications Protocol Draft Completed
  • Validations Protocol Draft Completed
  • COSA Registration