September
- Created Requirements and Justifications with sources
- Created Slide deck with Requirements and Justifications for presentation 1
- Revised Requirements and Justifications and added constraints
October
- Created Gantt chart based off initial
- Completed safety survey
- Took initial measurements of hospital beds
- Created Initial lifting devices based off lifting concept
- Added verifications and Validations based off of initial design ideas of Lifting machine
- Updated Budget chart for initial project of lifting device
- Generation of new winch Design based off of initial design concepts
- Generation of Device B and Requirements
- Generation of New Solidworks drawings for Device B, Device A, and Hospital table
- Creation of Decision Matrix of off Designs
- Presented initial design proposal
November
- Development of finalized design
- Created new idea to base budget off new device
- Development initial Anysis testing for table
- Creation of finalized budget based off of initial simulations
- Development of Abstract for device
December
- Initial final design completed
- Hazard Analysis completed
- Team presented final design to peers and faculty
- Completion of initial device design report
January
- Parts and budget finalized
- Parts ordered for device design
February
- NEBEC Abstract created
- Alterations made to Device A and setup
- Development of Testing protocol
March
- Final designs made for device A & B
- Verifications Protocol Draft Completed
- Validations Protocol Draft Completed
- COSA Registration