This year’s team would like to extend a HUGE thank you to one of our advisors, Regina Cadillac, who generously donated funds, equipment, and materials to ensure the successful completion of the project.
Month: February 2021
Manufacturing Begins…
As of 2/9/21, the complete frame materials have been received, along with numerous pieces for the drivetrain and steering systems. The team has begun manufacturing on all three of these systems, using tools such as the lathe, milling machine, drill press, mig welder, and more! Check out the “Photos” page for some manufacturing snapshots!

Report Submission
The team is happy to announce that they have submitted their Critical Design Report (CDR) to the ASME competition as of 1/26/21! A short presentation to ASME judges detailing their design will take place on 2/27/21!