Project Management Information

Project Budget

The budget appointed to us by the school is $270. This is because of a $90 budget for each member of the three-person group. For calculating cost, travel is not considered. Only the materials and components necessary for design are considered. With all that said, our group plans to use up to $250 dollars leaving a difference of $20. Our group decided to leave additional funds just in case it needs to be utilized for any repairs or changes to the design.

Project Timeline

The Gantt chart presents the timeline in which the group adhered to for BME assignment submissions, biomechanical analysis code development, prototyping, and other software code development. This is a living document. The chart only considers the Fall 2020 schedule and will be updated during Winter break 2020-2021 for the remainder of the academic year.

Gantt Chart Part 1/2
Gantt Chart Part 2/2