Project Updates


Documented below are month by month updates on the progress of this project, detailing the challenges and solutions that were faced.

September 2025
  • Requirements
  • Design Inputs
  • Website Created
  • Team Contract Created
  • Project Constraints

October 2025

  • Project Standards and Guidelines
  • Initial Budget Sheet
  • Gantt Chart
  • Safety Survey
  • Interim Design Review
    • Design Verification and Solutions

November 2025

  • Hazard Analysis
  • Project Abstract
  • SolidWorks Drawings and Initial Frame Model
  • Decisions for Functional Components
    • Motor, MCU, Tensioning Element, Materials, etc.

December 2025

  • Created more finalized SolidWorks models for the phase 2 shell based on updated design specs and drawings.
  • Found and acquired new parts and materials for the project
  • Final Design Review
    • Review of New Design models/drawings as well as testing methods
  • Developed full Scope design Verification and Validation Methods
  • Began to use OpenSim for the implemenation of design to measure actuation torques
    • Can be used for future validation methods