February 2018

During February, the team continued revisions of the initial draft for the Institutional Review Board. During the second week of February, project building started consisting of the exercise, heating, and headpiece components. The team collectively decided to make slight changes to verification protocol prior to IRB submission from the first semester report, in order to simplify the verification process. An updated timeline for the following months was also created to ensure the prototype is finished, along with testing. At the end of the month, the team reviewed the abstract for NEBEC and completed the FDA decision agreement. The final report was also started and updated throughout February from the first semester.