HEC-RAS

Design of the hydrological portion has begun. The bridge will be designed according to a 100 year storm along with high tide. The scour of the piles will be designed using a worst case scenario of a 500 year storm. Not only will the low chord of the bridge be designed for a 100 year storm but the asked height of 12 foot from the water level will be kept in mind for high tide.