Monthly Archives: April 2016

Approach Embankment

Figure 4a Approach Embankment Figure 4b Approach Embankment

A column supported embankment design method was selected for the approach embankment design.  In this design, 18″ diameter concrete columns will be spaced 8 feet center-to-center for the first 106 feet (starting at the bridge abutment).  After the first 106 feet, the spacing of the concrete columns increases to 10 feet center-to-center until the end of the approach.  The load transfer platform used in this design will be 3.25 ft thick.  The load transfer platform is used to distribute the load of the embankment to the columns below.  Additionally, Tensar Biaxial Geogrid BX1500 was selected as a reinforcement layer between the load transfer platform and the top of the concrete columns.  This reinforcement is necessary to prevent the columns from punching through the fill of the embankment.  Each approach embankment will require 105 18″ concrete columns and 7632 sq. feet of geogrid reinforcement.

Pier Design

The team has completed the final design for the size and configuration of the drilled shafts that will be used for all three piers. The following plan shows the dimensions and locations of the four 5 ft. diameter drilled shafts. They will also contain a 1/2″ thick permanent steel casing and be embedded 110 ft. into the soil. Untitled